PBS Energo AS v Bester Generacion UK Limited [2019] EWHC 996 (TCC)
Background
Bester and PBS were parties to a sub-contract for the engineering, procurement, construction and commissioning of a bio-mass fired energy plant in Wrexham.
Disputes later arose between the parties and the parties’ respective claims were then referred to Mr Tolson for adjudication. During the adjudication, Mr Tolson decided that PBS was entitled to terminate, and had validly terminated the sub-contract it had with Bester. He did not deal with the quantum of PBS’ claim but ordered that Bester repay the performance security of £2.7 million.
Bester did not pay, and PBS then commenced proceedings for summary judgment in order to enforce the adjudication. Stuart-Smith J gave judgment in favour of PBS, and PBS eventually received repayment of the performance security.
PBS then referred to adjudication the valuation of its claims. The total amount in milestone payments that PBS was entitled to under the sub-contract was £3.8 million. The adjudicator, Mr Judkins, decided that Bester was liable to pay PBS £1.7 million on the basis that he found that PBS had completed 43% of the contract works.
The present case concerns PBS’ application for summary judgment to enforce the award. Bester resists on the basis that the adjudication award was procured by fraud.
Alleged Fraud
According to Bester, PBS informed Mr Judkins that equipment manufactured for the Wrexham project had been stored to Bester’s order. That equipment would then be available to Bester upon payment of the sums due.
The relevance of the equipment is that Bester had previously made an argument that PBS could mitigate its losses by selling the equipment. Its entitlement should therefore be set off by the equipment it had ordered. This had been rejected by Mr Judkins, who stated that the equipment belonged to Bester and that Bester was responsible for collecting and disposing of it. It followed that the value of the equipment was part of the contract value of the work done by PBS in ordering it.
However, Bester claimed PBS’ representations were not true. A variety of equipment was not available upon payment of the sums due. Further, Bester alleged that PBS had been able to cancel its order for some equipment. Insofar as this was the case, PBS had overstated its claim and obtained the adjudication award by fraud.
Decision
Pepperall J, sitting in the TCC, held that it was properly arguable that the Judkins adjudication decision had been obtained by fraud.
On the facts of the case, it was clear that representations had been made to Mr Judkins that bespoke equipment had been ordered pursuant to the sub-contract with Bester for use on the Wrexham project and that the equipment would be made available. Those representation were false and there was good evidence that PBS knew they were false. It followed that PBS obtained an advantage in the adjudication and therefore obtained the decision by fraud.
Pepperall J was also satisfied that Bester could not have raised the fraud allegations during the adjudication as disclosure of the relevant documents in the underlying litigation had not been given to Bester in time for the fraud to be identified in the adjudication.
PBS had argued that even if credit was given for the equipment not ordered, there were still valuable equipment stored in good condition on Bester’s order. However, it was not for the court in a summary judgment application to “re-engineer Mr Judkin’s decision and to identify what, if any, sum might have been ordered to be paid in the event that there had been no arguable fraud.” PBS’ application was therefore not saved by proof that some valuable equipment was still stored in good edition.
Since severance of an adjudicator’s decision was not available, the fact that any part of decision was obtained by fraud meant that the adjudicator’s decision as a whole was invalid and unenforceable.
In addition, Pepperall J also distinguished the situation in the present case from the default position with respect to fraud and adjudication. In some instances, as in SG South Ltd v Kingshead Cirencester Ltd [2009] EWHC 2645 (TCC), an allegation of fraud may be relied upon as a defence to an adjudication. In instances where the defence of fraud to a claim has already been adjudicated, the adjudication award will typically be awarded. An adjudication will usually also be enforced where the allegation of fraud was not raised during the adjudication despite it being reasonably knowable at the time.
The difference, here, was that in this case the fraud was not a defence to PBS’ claim as such, but rather the adjudication award itself had been procured by fraud. Further, it was vital that the fraud was not reasonably discoverable at the time of the adjudication, and could therefore only be raised later at the application for summary judgment.
As Pepperall J states at paragraph [21]:
“The statutory policy of enforcing the temporary finality of an adjudication decision is important. As Fraser J rightly observed, the court must be robust not to allow such policy to be undermined simply by the assertion of fraud. In my judgment, such policy consideration must, however, yield to the well-established principle that the court will not allow its procedures to be used as a vehicle to facilitate fraud. Where, exceptionally, it is properly arguable on credible evidence that the adjudication decision was itself procured by a fraud that was reasonably discovered after the adjudication, the court is unlikely to grant summary judgment.”
For those reasons, PBS’ application for summary judgment was dismissed.
Disclaimer
This content is provided free of charge for information purposes only. It does not constitute legal advice and should not be relied on as such. No responsibility for the accuracy and/or correctness of the information and commentary set out in the article, or for any consequences of relying on it, is assumed or accepted by any member of Chambers or by Chambers as a whole.
Contact
Please note that we do not give legal advice on individual cases which may relate to this content other than by way of formal instruction of a member of Gatehouse Chambers. However, if you have any other queries about this content please contact: