Contributory negligence and construction contracts

Articles
10 Nov 2017

This article was first published on Practical Law’s Construction Blog.

A plethora of issues were raised, and disposed of, by Fraser J’s recently handed-down judgment in Riva Properties and others v Foster + Partners Ltd, the most awkwardly entertaining one being the sense of pantomime arising from the court’s clear disapproval of the architect’s behaviour, which was described at various stages as “grubby”, “disingenuous” and “wholly unprofessional”.

Putting pantomime reluctantly to one side (or perhaps “behind you…”), the crux of the case was that Fosters had been negligent when they advised their client that a design that would cost £195 million to carry out and complete could be “value engineered” down to £100 million, a mere £25 million more than the client’s original budget of £75 million. The expert evidence was that such value engineering would have been impossible and the judge awarded the claimant, or at least the first claimant, just over £3.5 million for the professional fees wasted on account of the negligence advice. The rather heftier claim for loss of profits (around £16 million), was dismissed on the basis that the claimant’s inability to secure funding for the project was partly attributable to his lack of cash reserves and to the 2008 global financial crisis.

However, I want to turn my attention to a relatively small aspect of the judgment concerning the defendant’s plea of contributory negligence and take the opportunity to remind us when it is possible to raise contributory negligence in the context of construction claims.

Contributory negligence

I won’t deal with the allegations themselves in any detail because they did not give rise to any particularly controversial points and were, in any event, dismissed in their entirety.

As to the principle at hand, the right to raise a plea of contributory negligence arises from section 1(1) of the Law Reform (Contributory Negligence) Act 1945, which states that:

“Where any person suffers damage as the result partly of his own fault and partly of the fault of any other person or persons… the damages recoverable in respect thereof shall be reduced to such extent as the court thinks just and equitable having regard to the claimant’s share in the responsibility for the damage.”

Section 4 of the Act defines “fault” as:

“… negligence, breach of statutory duty or other act or omission which gives rise to a liability in tort or would, apart from this Act, give rise to the defence of contributory negligence.”

That wording, as Fraser J recognised, gives rise to the possibility that contributory negligence can be raised by way of a defence even where a claim is brought exclusively in contract, so long as a concurrent duty in tort exists.

As Fraser J explained, the starting point where contributory negligence is raised against a professional, is to consider the nature of the defendant’s liability and the principles laid down by the Court of Appeal in the seminal case of Forsikringsaktieselskapet Vesta v Butcher.

Forsikringsaktieselskapet Vesta v Butcher

Prior to the judgment in Vesta, there had been some conflicting authority (both between English authorities and between English and Australian lines of thinking) about whether the Act could apply to a contractual claim.

However, in Vesta, the Court of Appeal upheld the decision of Hobhouse J (as he then was) and his finding that before deciding whether contributory negligence can be raised, it was necessary to consider into which of three categories a claim fell. The three categories he identified were:

  • Where the defendant’s liability arises from some contractual provision that does not depend on negligence on the part of the defendant.
  • Where the defendant’s liability arises from a contractual obligation that is expressed in terms of taking care (or its equivalent) but does not correspond to a common law duty to take care which would exist in the given case independently of contract.
  • Where the defendant’s liability in contract is the same as his liability in the tort of negligence independently of the existence of any contract.

The short answer is that contributory negligence cannot be raised where a case falls into the first two categories, and only in respect of category three where (as has been said above), there is concurrent liability in tort.

Interestingly, the Court of Appeal in Vesta included Neill LJ, who had come to a contrary decision in a slightly early case of AB Marintrans v Comet Shipping [1985] 1 WLR 1270 (namely that, in a claim for breach of contract, apportionment of liability under the Law Reform (Contributory Negligence) Act 1945 was not permissible). Neill LJ had commented that his conclusions as to the construction of the Act may well lead to unsatisfactory results in some cases. Indeed, the majority of academic commentators would tend to agree that it would be intolerably unjust if a claimant was allowed to escape the consequence of their own negligence, merely by being canny in the drafting and framing of their claim.

Need concurrent liability in tort

Therefore, in almost all claims involving the appointment of construction professionals (such as architects, surveyors, project managers and the like), where the relevant breach of contract would be co-extensive with a free-standing breach of a tortious duty, category three will apply and it will be possible for the defendant to raise contributory negligence regardless of how the claim is put. The only restriction will be a case where the contract specifically excludes liability in tort (and so the possibility of bringing a contrary claim in contributory negligence).

In the context of a construction contract, it is likely that a contract will fall into the second category, such that it would not be possible to raise contributory negligence, where you have a “simple” building contract of the type envisaged in Robinson v PE Jones (Contractors) Ltd. That is to say, a contract where the builder’s obligation is simply to build what they are told to build and it was not envisaged that the parties would be in a professional relationship, as would be the case with an architect, for example.

Of course, whether there has in fact been an assumption of responsibility under Hedley Byrne principles under a building contract, such that it moves from category two to three, will be a matter of fact and degree.

Author

Helena White

Call: 2007

Disclaimer

This content is provided free of charge for information purposes only. It does not constitute legal advice and should not be relied on as such. No responsibility for the accuracy and/or correctness of the information and commentary set out in the article, or for any consequences of relying on it, is assumed or accepted by any member of Chambers or by Chambers as a whole.

Contact

Please note that we do not give legal advice on individual cases which may relate to this content other than by way of formal instruction of a member of Gatehouse Chambers. However, if you have any other queries about this content please contact: